Streamlining Contract Management for the €2bn PALLAS Reactor with FastDraft™
Client
Industry
Solution
Duration
PALLAS is a new medical isotope reactor set to replace the ageing High Flux Reactor (HFR) in Petten. Designed to advance nuclear medicine and research, PALLAS will produce essential isotopes for diagnostics, therapy, and nuclear research. These isotopes will be transformed into radiopharmaceuticals to treat conditions such as cancer.
Preparatory enabling and piling works began in mid-2022, setting the stage for main construction. The primary facility will feature a building of 63 by 43 metres with a height of 21 metres, housing a 25 MW open-pool, uranium-fuelled reactor, and an adjoining L-shaped logistics building.
Additional infrastructure will include a four-storey support building with access and security controls, a four-storey office building, and a secondary cooling system facility. This cooling system will circulate water from the North Holland Canal through the reactor building, releasing it into the North Sea.
The Challenge
PALLAS had historically relied on traditional methods like spreadsheets and email to manage contracts, causing significant challenges. PALLAS were looking to switch to a suitable Contract Management System (CMS) for NEC4 contracts and were recommended FastDraft™ by an existing client, Lantis. They needed an intuitive system that would streamline contract management processes.
PALLAS had several key challenges they needed Built Intelligence to overcome. These included:
- High-paced project and delivery team inexperienced in working with NEC contracts.
- A CMS solution that was ISO27001 certified to provide high-quality data security
- Required a partner with extensive NEC experience to help implement the solution in under 8 weeks
- As a 5-year £800m project, PALLAS needed to know that the chosen CMS would not only have longevity but could also adapt and change to match the project requirements
- Provide onboarding support and training for a team that had not previously utilised contract management software
- A CMS that allows collaboration, reporting and contract health check analysis with customisability
Contract Solution
The NEC4 Engineering and Construction Contract (ECC) Option C is being employed by the joint delivery organisation.
The BI Toolkit Solution
PALLAS considered the options available in the market and recognised that FastDraft™ was the CMS most capable of managing the immense complexity of the project while simultaneously making the NEC4 Contract delivery process and collaboration as clear and user-friendly as possible.
Using an agile implementation methodology the BI Team were able to successfully deliver all required client outputs within six weeks, including:
- Hosting meetings with client experts to ensure all contractual variations were captured
- Building customisable FastDraft™ workflows that mirrored any amendments within their NEC4 contract
- Designing and hosting training sessions with the core project team to introduce them to NEC4 and FastDraft™
- Securing Single Sign-on (SSO) and Multi-Factor Authentication (MFA) access for the project team
- Integrating FastDraft™ with third-party systems like Sharepoint
Outcomes
- The flexibility to manage and maintain the platform settings to get new projects and users up and running promptly saving time with online training aids
- Allowed the team to hit the ground running once the project started
- Sped up learning how to use the system as there wasn’t a language barrier
- Ensures compliance to reduce risk and costs which has helped improve financial and operational performance whilst minimising risk
Looking for a more consistent way to manage contracts across projects and supply chain?
Continue Reading
How Speller Metcalfe Brought Greater Control to Contract and Subcontract Management with FastDraft™
[digr_content_grid_item title="Client" button_url_new_window="1" item_align="on" alignment="center" _builder_version="4.27.5" _module_preset="default"...
How BAM Streamlined Contract Management Across Their Supply Chain
[digr_content_grid_item title="Client" button_url_new_window="1" item_align="on" alignment="center" _builder_version="4.27.5"...
How National Grid Ventures Improved Contract Portfolio Visibility with FastDraft™
[digr_content_grid_item title="Client" button_url_new_window="1" item_align="on" alignment="center" _builder_version="4.27.4"...
