JCT Contracts Explained: What They Are and How They Work

 

A JCT contract is a standard form construction contract published by the Joint Contracts Tribunal (JCT). It sets out the rights, obligations, risk allocation, payment terms and timescales agreed between the client, known in the contract as the Employer, and the Contractor carrying out the work. 

 

JCT contracts are widely used across UK building work, particularly in the private sector. The current version is the 2024 Edition, and the 2016 Edition was withdrawn on 31 March 2026. Projects that had already started or gone to tender on 2016 forms can still be contracted on them until 31 December 2026. 

 

This guide covers the main contract types, how to identify the one you are working under, and what the contract requires of each party from signature to the Final Certificate. 

What is a JCT Contract?

 

A JCT contract is a pre-drafted set of terms that both parties, and their advisers, already recognise. Using a standard form saves the cost of drafting bespoke terms and makes tenders easier to price, because contractors know the risk they are taking on. It also reduces arguments about what the words mean, since many JCT provisions have been interpreted by the courts over several decades. 

JCT contracts are not a single document. Each contract family includes a main contract, matching sub-contracts, collateral warranties and guidance notes, so the same terms can flow down the supply chain. 

In RIBA’s Construction Contracts and Law Report 2022, 59% of respondents said JCT was the contract family their organisation used most often, and 71% had used a JCT contract in the previous 12 months. NEC contracts are more common on public sector and infrastructure work, and the differences between the two are set out further down. 

Who is the Joint Contracts Tribunal?

 

The Joint Contracts Tribunal has produced standard forms of building contract since 1931. It is sometimes called the joint contract tribunal, although the correct name refers to contracts in the plural. 

JCT forms are drafted with input from across the industry through seven member bodies: 

  • Build UK 
  • Contractors Legal Grouping 
  • Local Government Association 
  • Real Estate:UK (formerly the British Property Federation) 
  • Royal Institute of British Architects (RIBA) 
  • Royal Institution of Chartered Surveyors (RICS) 
  • Scottish Building Contract Committee (SBCC) 

The SBCC publishes Scottish versions of the main JCT contracts, adapted for Scots law. 

 

The JCT 2024 Edition: what’s current and what changed

 

The 2024 Edition is the current suite of JCT contracts. Design and Build was the first family released, in April 2024, and the rollout finished in June 2025 with a new Target Cost Contract. The Home Owner contracts are the exception and remain on their 2021 versions. 

The 2016 Edition was withdrawn on 31 March 2026. Projects that had already started or gone to tender on 2016 forms can still be contracted on them until 31 December 2026, after which 2016 forms can no longer be bought. A contract signed on a 2016 form remains a 2016 contract for the whole project, so check the edition before relying on a clause number or time limit, as both changed in places. 

The changes that most affect day-to-day administration are: 

  • Building Safety Act 2022: the Articles now name the Principal Designer and Principal Contractor, reflecting the dutyholder roles introduced under the Building Safety Act 2022. 
  • New Relevant Events and Relevant Matters: the discovery of asbestos, contaminated material or unexploded ordnance, epidemics, and changes in law or published guidance are now Relevant Events, the events that entitle the Contractor to more time. Epidemics and changes in law only become Relevant Matters, which carry a right to loss and expense, if selected in the Contract Particulars. 
  • Faster extension of time decisions: the period for deciding an extension of time has been reduced from 12 weeks to 8. 
  • Notices by email: notices can be served electronically if the Contract Particulars allow it. 
  • Collaboration, sustainability and dispute notification: previously optional supplemental provisions are now core terms, including a requirement to notify a likely dispute so senior representatives can try to resolve it.

JCT contract types: which form are you working under?

 

JCT publishes its building and construction contracts in families, one for each common procurement route. The right one for a project depends on who is designing, how the work will be procured and how complex and well defined it is. JCT does not set value limits for any of its forms, so project size alone should not decide the choice.

 

Contract family  Typically used for  Who designs  Who administers for the Employer 
Standard Building Contract (SBC/Q, SBC/XQ, SBC/AQ)  Large or complex projects procured traditionally  Employer’s team, with an optional Contractor’s Designed Portion  Architect/Contract Administrator, with a Quantity Surveyor 
Intermediate Building Contract (IC, ICD)  Fairly detailed work without complex services or specialist work  Employer’s team (ICD adds contractor design for specified parts)  Architect/Contract Administrator 
Minor Works Building Contract (MW, MWD)  Smaller, simple work  Employer’s team (MWD adds contractor design for specified parts)  Architect/Contract Administrator 
Design and Build Contract (DB)  Projects where the Contractor designs and builds  Contractor, often developing the Employer’s concept  Employer’s Agent 
Major Project Construction Contract (MP)  Large design and build projects between experienced parties  Contractor  Employer’s Representative 
Target Cost Contract (TCC)  Projects where savings and overruns are shared against a target cost  Contractor  Employer or appointed Employer’s Agent 
Management Building Contract (MC)  Management contracting  Employer’s team  Architect/Contract Administrator  
Construction Management (CM/A, CM/TC)  Projects where the Employer contracts trade contractors directly  Employer’s team  Construction Manager 
Prime Cost Building Contract (PCC)  Early starts, alterations or urgent work paid at cost plus a fee  Employer’s team  Architect/Contract Administrator 
Measured Term Contract (MTC)  A regular flow of maintenance and minor works over a set term  Employer  Contract Administrator 
Repair and Maintenance Contract (RM)  A defined programme of repair and maintenance  Employer  Employer (no independent administrator) 
JCT Constructing Excellence (CE)  Partnering and collaborative working  Varies by project  Project team (parties are called Purchaser and Supplier) 
Home Owner contracts (HO/B, HO/C, HO/RM)  Work for homeowners  Not applicable  Homeowner, or a consultant under HO/C 

 

Each main contract has matching sub-contracts, so the terms the Contractor agrees with the Employer can be passed down to its supply chain. Collateral warranties extend the Contractor’s or a sub-contractor’s obligations to third parties such as funders, purchasers and tenants. 

The Academy course Introduction to JCT Procurement and the Contract explains how the procurement route shapes the choice of form. 

 

How a JCT agreement is structured

 

Most JCT main contracts follow the same three-part layout: 

  • The Agreement: the Recitals describing the project, the Articles naming the parties and key appointments, the Contract Particulars, and the attestation, where the parties sign. 
  • The Conditions: the main terms, grouped into numbered sections covering definitions, carrying out the Works, control of the Works, payment, Variations, insurance, assignment and third party rights, termination, and settlement of disputes. 
  • The Schedules: supporting provisions such as insurance options, bond forms and fluctuations options. 

The way the Agreement is executed also affects how long claims can be brought. Under the Limitation Act 1980, a contract executed as a deed carries a 12-year limitation period, compared with 6 years for one signed as a simple contract.

 

The Contract Particulars: what to check first 

 

The Contract Particulars record the project-specific choices many clauses depend on. A blank entry usually triggers a default that may not suit the project. Check these first: 

  • Date of Possession and Date for Completion: the start and finish dates the Contractor is measured against, including any Sections. 
  • Liquidated damages: the rate the Employer can deduct for late completion. 
  • Interim Valuation Dates and retention: when valuations take place and the percentage of retention to be deducted, where applicable. Retention provisions and default percentages vary between JCT contract forms and should be checked against the relevant contract. 
  • Rectification Period: how long the Contractor remains responsible for putting right defects after practical completion. 
  • Insurance option: Option A, B or C, which sets out who insures the Works and whether existing structures are involved. 
  • Electronic notices: whether notices can be served by email. 
  • Epidemics and changes in law: whether they count as Relevant Matters as well as Relevant Events. 

The Academy course Introduction to JCT Setting up the Contract works through these entries in more detail.

 

 

How a JCT contract works once it’s signed

 

Under the traditional forms (SBC, IC and MW), the Architect/Contract Administrator issues instructions and certificates, the Quantity Surveyor values the work, and the Contractor gives the notices the contract requires. The Architect/Contract Administrator is appointed by the Employer but must certify fairly between the parties.  

Design and Build has no independent certifier, and the Employer’s Agent acts for the Employer. In practice, many JCT disputes turn on process rather than wording, such as a notice served late, a certificate never issued or a record too thin to support a claim.

 

Payment: valuations, notices and the final date

 

Payment under a JCT contract runs throughout the project, usually monthly, not only at completion. Under the Standard Building Contract the cycle works as follows. 

 

Step  When  Who 
Interim Valuation Date  Monthly, as set in the Contract Particulars  Quantity Surveyor values the work 
Due date  7 days after each Interim Valuation Date  Fixed by the contract 
Interim Certificate (the payment notice)  Within 5 days of the due date  Architect/Contract Administrator 
Pay Less Notice  No later than 5 days before the final date for payment  Employer 
Final date for payment  14 days after the due date  Employer 

These timings reflect the payment rules in the Housing Grants, Construction and Regeneration Act 1996, as amended by Part 8 of the Local Democracy, Economic Development and Construction Act 2009. If an Interim Certificate is not issued within the required period, a compliant Contractor’s payment application may become the payment notice. Where no such application was submitted, the Contractor may issue a payment notice in accordance with the contract, which can affect the final date for payment. 

Either party can refer a payment dispute to adjudication at any time under section 108 of the 1996 Act.

 

Extensions of time and Relevant Events

 

 

 

The Contractor must notify the Architect/Contract Administrator as soon as it becomes reasonably apparent that progress is being, or is likely to be, delayed. The notice should give the cause, the expected effect and an estimate of any delay to completion. An extension of time is only available where the cause is a Relevant Event, such as: 

  • Variations instructed under the contract 
  • Impediment, prevention or default by the Employer or anyone acting for it 
  • Exceptionally adverse weather 
  • Discovery of asbestos, contaminated material or unexploded ordnance 
  • Epidemics 

The 2024 Edition gives the Architect/Contract Administrator 8 weeks from receiving the required particulars to fix a new Completion Date. If the Works then finish late, the Employer can recover liquidated damages, but under the Standard Building Contract a Non-Completion Certificate is one of the conditions for deducting them, so a missed certificate puts that deduction at risk. 

Each of these steps depends on a dated, traceable record. FastDraft’s JCT Contract Management Software holds changes, Relevant Events and extension of time assessments in one place with an audit trail, and the Academy course Introduction to JCT Contract Administration Time covers the time provisions in detail.

 

 

Loss and expense and Relevant Matters 

 

 

JCT deals with time and money separately, and an extension of time does not bring any payment with it. To recover loss and expense, the Contractor must make a separate application linked to a Relevant Matter as soon as the likely effect becomes reasonably apparent, supported by records. 

The two lists overlap but are not identical. Exceptionally adverse weather, for example, entitles the Contractor to more time but not to loss and expense. 

 

 

Completion and the Final Certificate 

 

 

Completion runs through a sequence of certificates: 

  • Practical completion certificate: issued when the Works are practically complete. It starts the Rectification Period and releases half of the retention. 
  • Certificate of making good: issued following the making good of defects identified under the contract, generally triggering the release of the remaining retention, subject to the applicable contractual provisions. 
  • Final Certificate: confirms the final adjusted contract sum. Under the Standard Building Contract it becomes conclusive on certain matters unless proceedings are started within the period the contract allows. 

 

 

JCT vs NEC: what’s different if you’re used to NEC

The biggest differences for NEC users are who manages the contract and how time and money are handled. 

 

Area  JCT  NEC4 
Contract administrator  Architect/Contract Administrator certifies independently, with a more limited management role  Project Manager actively manages the contract on the Client’s behalf 
Early warning  No equivalent mandatory early warning procedure under the standard forms, although contractual notification obligations still apply.  Early warnings under clause 15 
Programme  Limited contractual role  The Accepted Programme is central to assessing change 
Time and money  Relevant Events and Relevant Matters assessed separately  Compensation events assess time and cost together 
Typical use  Private sector building work  Public sector and infrastructure work 

 

Neither form is better in the abstract. The right choice depends on the client, the project and how actively the team intends to manage it. For the NEC side of the comparison, see NEC contracts explained. 

Getting support with your JCT contracts

Built Intelligence supports teams working under JCT contracts in three ways: 

 

This article is general information about JCT contracts and is not legal advice. Take advice on the specific terms of your contract. 

JCT contract FAQs

 

 

Can I still use a JCT 2016 contract? 

 

Contracts already signed on 2016 forms continue under those terms until the project ends. Projects that had already started or gone to tender on 2016 forms before the withdrawal can still be contracted on them until 31 December 2026. New projects should use the 2024 Edition.

 

How much does a JCT contract cost? 

 

JCT sells its contracts individually, in print and digital formats, and through its JCT On Demand online service. Prices vary by contract family and format, so check JCT’s current price list before budgeting. 

 

What are the downsides of a JCT contract?

 

JCT contracts are detailed and procedural, so they reward careful administration and penalise missed deadlines, particularly for payment and extension of time notices.

 

Handling time and money separately can lengthen the resolution of claims. Heavy amendments also erode the main benefit of a standard form, because each change moves risk away from a position both sides already understand. 

 

Can JCT contracts be amended? 

 

Yes. Many clients amend JCT contracts, usually through a schedule of amendments. Every amendment changes the risk allocation the form was designed around, so limit amendments to what the project needs and make sure the team administering the contract knows which clauses have changed. 

 

JCT Guide

Download the full JCT Beginner’s Guide

10 Nov, 2026
Training budgets: an investment in capability, consistency and cost control

Training budgets: an investment in capability, consistency and cost control

A training budget should not be seen only as a cost to control. Used well, it is an investment in reducing risk, improving consistency and building the capability people need to perform effectively. For organisations managing complex projects and contracts, targeted learning can reduce avoidable mistakes, strengthen business knowledge and address capability gaps before they become costly.  A strong training budget directs investment towards the capability gaps that create the greatest operational and commercial risk.  Why training investment matters Without the right training, employees can lose time searching for answers, repeating work, or escalating issues that could have been handled earlier. In contract management, knowledge gaps can also increase the risk of missed obligations,...

read more
Continuous learning: an investment that can reduce business costs

Continuous learning: an investment that can reduce business costs

In construction and contract management, knowledge gaps can quickly become expensive. Missed notices, poor record-keeping, misunderstood contract obligations and inconsistent processes can lead to delays, rework, disputes and avoidable risk. Continuous learning helps teams keep their knowledge current, apply it confidently and make better decisions before small issues become costly problems.  A strong continuous-learning programme is more than occasional training. It gives people access to relevant, practical learning, supports them with expert guidance, and helps organisations track development so capability improves over time. Four ways continuous learning can save money   1. Reduce avoidable errors and rework When employees understand contract requirements, commercial processes...

read more
NEC Contract Guide: NEC Contracts Explained

NEC Contract Guide: NEC Contracts Explained

Table of contents   What is NEC? Types of NEC Contracts NEC4 Options Explained Key roles & responsibilities Common NEC mistakes by first-time users First 90 days checklist NEC is a family of standard form contracts widely used on UK construction and infrastructure projects. NEC4 is the latest generation of the suite. For anyone working under one for the first time, the language and structure take some getting used to. This guide sets out what that means in practice: how NEC4 differs from NEC3, what the main contract types and options are for, and what to get right in the first few weeks so the contract works the way it's designed to.  What is an NEC Contract?   The New Engineering Contract, or NEC, is not one single contract but a family of standard contracts used...

read more

62 Prince St, Bristol BS1 4QD

Citb Logo
Cyber essentials Logo
Gcloud Logo
ISO 9001 Logo
ISO 14001 Logo
ISO 27001 Logo

Built Intelligence Ltd is a company registered in England and Wales with company number 08323228. Company registered office address 3rd Floor Mariner House, 62 Prince Street, Bristol, BS1 4QD. VAT number 172429407.

© 2026 Built Intelligence Ltd.