1
/
of
1
Osborne Clarke
You can smash but not always grab when manifestly unjust
You can smash but not always grab when manifestly unjust
Couldn't load pickup availability
This course focuses on the factual circumstances surrounding the issue of payment notices in relation to a "smash and grab" adjudication.
The Technology and Construction Court (TCC) has confirmed that this may justify a stay of execution of an adjudication award where enforcement would result in manifest injustice.
By the end of this course, you should be able to:
- Understand the case of JRT v TWD and how smash and grab adjudication was possible
- Describe how The Technology and Construction Court (TCC) granted the stay of execution on both grounds of the case